Is a Data Center Coming

Muscogee County, GA

Project Ruby

Muscogee Property 1 LLC (Habitat Real Estate Partners and Atlas Development). Rumored. 600 MW.

Project Ruby is a proposed hyperscale data center campus targeting about 865 acres of wooded land near Skyler Drive in the Upatoi area of northeastern Muscogee County, bordering Harris and Talbot counties, with reported investment above 5 billion dollars and a requested 600 megawatt grid connection from Flint Energies, though some reports cite figures as high as 900 megawatts and up to 987 acres. Developers Habitat Real Estate Partners and Atlas Development have not yet filed the actual rezoning request for the site itself. Columbus City Council passed a technology overlay ordinance on June 16, 2026 that would allow a project like this to proceed if the developer's rezoning application is later approved, and the plan has drawn large, vocal town halls and a downtown rally against it in July 2026.

Status
Rumored
Operator
Not disclosed
Applicant on record
Muscogee Property 1 LLC (Habitat Real Estate Partners and Atlas Development)
Location
near Skyler Drive, Upatoi community, northeastern Muscogee County, Columbus, Muscogee County, GA (approximate, city center)
Size
600 MW, 865 acres
Cooling
Not reported
Utility
Flint Energies
First reported
2026-02
Last updated
July 21, 2026

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 600 MW facility would draw roughly 1.9 million to 6.8 million gallons of water a day, about what 21,900 households use.

Base rate freeze through 2028 (docket 44280) holds base rates flat from July 2025. Fuel and storm riders are separate and can still move. 2026 fuel and storm cost settlement (docket 44280, 56765) takes about $4.04 a month off a typical bill from June 2026. The December 2025 certification of about 9,885 MW of new generation for data center load came with a promise of at least $8.50 a month of downward pressure on a typical bill in 2029 through 2031, because large customers are meant to carry more of the cost. Consumer groups warned it could instead add around $20 a month if the projected data center demand does not show up.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

DLI ONE DLI ONE
9.1 mi SWOperatingMuscogee County, GA

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.