Is a Data Center Coming

Williamson County, TX

Blueprint Georgetown Data Center

Blueprint Data Centers. Under construction. 25 MW.

Blueprint Data Centers is investing 160 million dollars in a Georgetown facility off Westinghouse Road, about 45,000 square feet on 10 acres with up to 25 megawatts of power, tied to the company's Taylor area expansion. The first phase is expected online by late 2026 with full completion by early 2027.

Status
Under construction
Operator
Blueprint Data Centers
Applicant on record
Blueprint Data Centers
Location
Westinghouse Road, Georgetown, TX, Williamson County, TX
Size
25 MW, 10 acres, 45,000 sq ft
Cooling
Not reported
Utility
Georgetown Utility Systems
First reported
2026
Last updated
August 19, 2026

What happens next

The site is under construction. The next step is opening.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 25 MW facility would draw roughly 79,000 to 285,000 gallons of water a day, about what 900 households use.

For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.

Other tracked projects within 25 miles

Thin-nology Operator not disclosed
16 mi SOperatingTravis County, TX

Common questions

Where is the Blueprint Georgetown data center?

It is in Georgetown, Williamson County, TX.

Has the Blueprint Georgetown data center been approved?

Yes, it was approved and is now under construction.

How big is the Blueprint Georgetown data center?

Reported size: 25 MW, 10 acres, 45,000 square feet.

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.