Edged Atlanta (Tilford Yard)
Edged Energy. . 168 MW.
Edged Energy opened the first building of a planned three building, 168 megawatt data center campus at the former Tilford Yard site at 1800 Thomas Street NW in Atlanta, with a grand opening on August 21, 2024. The facility uses waterless, air based cooling technology designed for AI and cloud computing workloads and was described as Edged's first ultra efficient North American data center.
Follow this project
One free email when Edged Atlanta (Tilford Yard) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get an address report.
- Status
- Operator
- Edged Energy
- Applicant on record
- Edged Energy
- Location
- 1800 Thomas Street NW (Tilford Yard), Atlanta, Fulton County, GA
- Size
- 168 MW
- Cooling
- Air cooled
- Utility
- Not reported
- Last updated
- August 21, 2024
What happens next
The site is operating. A future expansion would show up here as a status change, or as a new project nearby.
Sources
- Edged Data Centers Celebrates Grand Opening of New Ultra-Efficient, Sustainable Data Center in Atlanta, PR Newswire, 2024-08-21
- Edged Data Centers Opens First Ultra-Efficient North American Data Center in Atlanta, Data Center Frontier, 2024-08-21
What it would mean nearby
Base rate freeze through 2028 (docket 44280) holds base rates flat from July 2025. Fuel and storm riders are separate and can still move. Real-time pricing revenue credit and cost allocation review (docket 57171) is pending before the commission without a published residential figure yet. 2026 fuel and storm cost settlement (docket 44280, 56765) takes about $4.04 a month off a typical bill from June 2026.
For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.
Other tracked projects within 25 miles
Common questions
Where is the Edged Atlanta (Tilford Yard) data center?
It is in Atlanta, Fulton County, GA.
How big is the Edged Atlanta (Tilford Yard) data center?
Reported size: 168 MW.
Is it near you?