Added as denied
Former Hynix Plant Data Center Proposal (Denied)
Operator not disclosed. Denied
An attorney representing an unnamed client asked the city of Eugene in July 2026 whether a data center would be allowed at the shuttered 1.2 million square foot Hynix semiconductor plant on 200 acres in west Eugene. The city's planning director ruled on September 8, 2026 that a modern data center does not fit the site's Campus Employment zoning, saying the information technology services category in Eugene's code, written in 2001, was never meant to cover large scale data centers. The decision can be appealed to the state Land Use Board of Appeals, and it comes as Eugene residents have separately called for a citywide data center moratorium.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Former Hynix Plant Data Center Proposal (Denied) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Denied
- Operator
- Not disclosed
- Location
- 1830 Willow Creek Circle, Eugene, OR, Lane County, OR
- Size
- MW not reported, 200 acres, 1,200,000 sq ft
- Cooling
- Not reported
- Utility
- Eugene Water & Electric Board
- First reported
- 2026-07
- Last updated
- September 24, 2026
What happens next
This proposal will not move forward as filed, but the land it was proposed on can be proposed again under a new project. See other stopped projects.
Sources
- Data center not permitted under zoning of former Hynix factory, city says, Lookout Eugene-Springfield, 2026-09-08
- Eugene says zoning doesn't allow data centers at former Hyundai/Hynix campus, KLCC, 2026-09-09
- Eugene blocks data center at old Hynix plant, KEZI
History
Other tracked projects within 25 miles
Common questions
Where is the Former Hynix Plant data center?
It is in Eugene, Lane County, OR.
Has the Former Hynix Plant data center been approved?
No. A local government denied it.
How big is the Former Hynix Plant data center?
Reported size: 200 acres, 1,200,000 square feet.
Corrections and tips: use the address in the footer. We link every claim to its source.