Fundamental Ridgeline Data Center Energy Campus
Fundamental Data. On hold, 1656 MW
Fundamental Data has proposed a data center and off grid natural gas power plant, called the Ridgeline Facility, on land it describes as part of a complex of up to 10,000 acres between Tucker and Grant counties, about a mile from the tourist towns of Thomas and Davis. The company has applied for a state air permit, and its project is the type meant to use West Virginia's 2025 House Bill 2014 certified microgrid and data center law, which lets certified projects bypass most local zoning control. In mid-2026 the state Department of Commerce notified Fundamental Data it was in violation of HB 2014 for not filing its high impact data center certification application, and the state Department of Environmental Protection has separately questioned the company's control of the proposed site.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Fundamental Ridgeline Data Center Energy Campus changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- On hold
- Operator
- Fundamental Data
- Applicant on record
- Fundamental Data
- Location
- Davis, Tucker County, WV (approximate, city center)
- Size
- 1656 MW
- Cooling
- Not reported
- Utility
- Not reported
- Last updated
- September 24, 2026
What happens next
Paused by the developer, a regulator, or a court. It could resume, be withdrawn, or be replaced by a new filing on the same land.
Sources
- DEP questions Fundamental Data site control for Tucker Co. data center-linked project, West Virginia Press Association
- Fundamental Data worker says company wrote WV data center law, urges project guardrails in own town, West Virginia Watch, 2026-07-22
- Fundamental Ridgeline Data Center, Cleanview
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 1656 MW facility would draw roughly 5.2 million to 18.9 million gallons of water a day, about what 60,400 households use.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
History
Common questions
Where is the Fundamental Ridgeline Data Center Energy Campus?
It is in Davis, Tucker County, WV.
Has the Fundamental Ridgeline Data Center Energy Campus been approved?
Not yet. It is on hold.
How big is the Fundamental Ridgeline Data Center Energy Campus?
Reported size: 1656 MW.