HostDime. Under construction.

HostDime is building SuperNova, a seven story, roughly 100,000 square foot Tier IV data center and company headquarters on a five acre parcel at 1 Innovative Place near Interstate 4 between Maitland and Eatonville in the Orlando area. The roughly 60 million dollar project broke ground with Robins & Morton as construction manager and was originally expected to open in early 2026, with more recent company updates pointing to a second quarter 2026 opening. The company says it will be the only enterprise grade Tier IV data center in Central Florida.

Status
Under construction
Operator
HostDime
Applicant on record
HostDime
Location
Maitland, Orange County, FL (approximate, city center)
Size
MW not reported, 5 acres, 100,000 sq ft
Cooling
Not reported
Utility
Not reported
Last updated
September 24, 2026

What happens next

The site is under construction. The next step is opening.

Sources

History

September 25, 2026

Added as under construction

Other tracked projects within 25 miles

E-Foam Operator not disclosed
12 mi WOperatingOrange County, FL

Common questions

Where is the HostDime SuperNova data center?

It is in Maitland, Orange County, FL.

Has the HostDime SuperNova data center been approved?

Yes, it was approved and is now under construction.

How big is the HostDime SuperNova data center?

Reported size: 5 acres, 100,000 square feet.

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.