PathOne Data Center (Former Bison Plant Site)

PathOne Data Centers. On hold. 10 MW.

PathOne Data Centers and Sunstone Investments want to build a roughly 40,000 square foot, 10 megawatt data center on the old Bison Plant site about two miles southwest of Hull, with room to grow toward 25 megawatts. Sioux County put a one year moratorium on new data centers in place, and developers told the county an end user had already been lined up before that happened. PathOne held a public meeting in Hull on August 25, 2026 even though the moratorium was still in effect.

Status
On hold
Operator
PathOne Data Centers
Applicant on record
PathOne Data Centers
Location
Hull, Sioux County, IA (approximate, city center)
Size
10 MW, 40,000 sq ft
Cooling
Not reported
Utility
Not reported
First reported
2026-06
Last updated
August 29, 2026

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 10 MW facility would draw roughly 32,000 to 114,000 gallons of water a day, about what 400 households use.

For a noise estimate and the three distance rings, check your own address.

Follow this project

One email when PathOne Data Center (Former Bison Plant Site) changes status or a new filing lands within 25 miles of it.

Unsubscribe with one click. We do not sell the list.

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.