Microsoft. Filed. 325 MW.

Microsoft paid Xcel Energy 17.7 million dollars for nearly 300 acres next to Xcel's Sherco power plant in Becker, Sherburne County, in a deal that closed in February 2024, for a data center planned at up to 325 megawatts. Amazon separately bought an adjacent 348 acre parcel from Xcel for a second data center project in the same area. Neither company has publicly reported a construction start date, and no site plan or permit hearing was found in local coverage for this entry.

Status
Filed
Operator
Microsoft
Applicant on record
Microsoft
Location
Becker, Sherburne County, MN (approximate, city center)
Size
325 MW, 300 acres
Cooling
Not reported
Utility
Xcel Energy
First reported
2024-02
Last updated
September 24, 2026

What happens next

Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 325 MW facility would draw roughly 1.0 million to 3.7 million gallons of water a day, about what 11,800 households use.

For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.

History

September 25, 2026

Added as filed

Other tracked projects within 25 miles

Common questions

Where is the Microsoft Becker data center?

It is in Becker, Sherburne County, MN.

Has the Microsoft Becker data center been approved?

Not yet. An application has been filed and has not been decided.

How big is the Microsoft Becker data center?

Reported size: 325 MW, 300 acres.

Is it near you?