Douglas County, GA
Microsoft Douglasville Data Center (FTY101)
Microsoft. Under construction.
Microsoft is building a four building, roughly 980,000 square foot data center campus known as FTY101 on 160 acres at 1601 North River Road in Douglasville, part of its East US 3 Azure region that also includes sites in Fulton County. On August 10, 2026 Microsoft confirmed it is unwinding local property tax abatement deals here and at two Fulton County sites, East Point and Palmetto, saying the reputational cost of the tax breaks now outweighs the savings. Some third party trackers report a target capacity around 300 megawatts for this site, but that figure has not been independently confirmed by Microsoft or the county.
- Status
- Under construction
- Operator
- Microsoft
- Applicant on record
- Microsoft
- Location
- 1601 North River Road, Douglasville, Douglas County, GA
- Size
- MW not reported, 160 acres, 980,000 sq ft
- Cooling
- Not reported
- Utility
- Not reported
- Last updated
- August 10, 2026
Sources
- Microsoft aiming to build 1 million sq ft data center in Douglasville, GA, Elevate Douglas Economic Partnership
- Fulton County votes unanimously to oppose data center tax incentives as Microsoft unwinds deals at 3 Atlanta sites, dmnews.com, 2026-08-10
What it would mean nearby
Oglethorpe Power, which generates most of the electricity Georgia's EMCs sell, is adding natural gas plants it ties to data center and industrial load. EMC rates are set by each cooperative's board, not the Public Service Commission, so watch your EMC's rate notices.
For a noise estimate and the three distance rings, check your own address.
Other tracked projects within 25 miles
Is it near you?
Corrections and tips: use the address in the footer. We link every claim to its source.