Added as under construction
Microsoft Malaga Data Center Campus
Microsoft. Under construction. 298 MW.
Microsoft is building a six building data center campus of roughly 105 acres in Malaga, near Pangborn Memorial Airport, after Chelan County PUD commissioners approved a power contract in June 2025 that grew to as much as 298 megawatts of infrastructure capacity through 2030 under a 14 year term. Microsoft paid for an 86.5 million dollar substation, called Jumpoff Ridge, and related grid upgrades to serve the site, and the first building was expected to begin phased operations around August 2026 with up to 16 megawatts of mostly carbon free, surplus hydropower. The remaining buildings are still under development as the utility and Microsoft work out longer term power supply terms through 2040.
Follow this project
One email when Microsoft Malaga Data Center Campus changes status or a new filing lands within 25 miles of it.
Renews yearly until you cancel. Cancel any time from any email. We do not sell the list.
Buying or living near this site? Get an address report.
- Status
- Under construction
- Operator
- Microsoft
- Applicant on record
- Microsoft
- Location
- Malaga, Chelan County, WA (approximate, city center)
- Size
- 298 MW, 105 acres
- Cooling
- Not reported
- Utility
- Chelan County PUD
- First reported
- 2025-06
- Last updated
- September 24, 2026
What happens next
The site is under construction. The next step is opening.
Sources
- Chelan County PUD commissioners OK energy contract with Microsoft for Malaga data center buildings, Wenatchee World, 2025-06-17
- Chelan PUD: PUD commissioners approve power contract for Microsoft data center, Chelan County PUD, 2025-06-17
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 298 MW facility would draw roughly 945,000 to 3.4 million gallons of water a day, about what 10,900 households use.
For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.
History
Other tracked projects within 25 miles
Common questions
Where is the Microsoft Malaga data center?
It is in Malaga, Chelan County, WA.
Has the Microsoft Malaga data center been approved?
Yes, it was approved and is now under construction.
How big is the Microsoft Malaga data center?
Reported size: 298 MW, 105 acres.
Is it near you?
Corrections and tips: use the address in the footer. We link every claim to its source.