Project Eisenhower
QTS Data Centers (filed as Eagle South LLC). Under construction.
Originally filed in January 2022 by T5 Data Centers as a four building, 1.67 million square foot, roughly 200 megawatt campus off Gordon Highway, the project is now controlled by QTS Data Centers, Blackstone owned, through Eagle South LLC, and has expanded to six two story buildings totaling more than 2.15 million square feet across about 140 acres, a roughly 2 billion dollar investment. Site clearing, home demolition, and earth moving were underway through 2025 and into 2026 next to the Haynes Station and Captains Corner neighborhoods, and Augusta put a temporary hold on new data center approvals in mid 2026 that does not apply to this already approved project. QTS says the facility will use closed loop cooling that does not draw water once operating, but neighbors have complained about a lack of communication before construction began.
Follow this project
One free email when Project Eisenhower changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get an address report.
- Status
- Under construction
- Operator
- QTS Data Centers
- Applicant on record
- Eagle South LLC
- Location
- 2865-2883 Gordon Highway, Augusta, Richmond County, GA
- Size
- MW not reported, 140 acres, 2,150,000 sq ft
- Cooling
- Closed loop (low water)
- Utility
- Not reported
- First reported
- 2022-01
- Last updated
- June 2, 2026
What happens next
The site is under construction. The next step is opening.
Sources
- Augusta puts a hold on data centers, except the one that's riled up neighbors, WRDW, 2026-06-02
- Flying under radar, new data center will be twice as big as Augusta Mall, WRDW, 2025-12-26
- QTS targets two data center campuses in Georgia, Data Center Dynamics
What it would mean nearby
Base rate freeze through 2028 (docket 44280) holds base rates flat from July 2025. Fuel and storm riders are separate and can still move. Real-time pricing revenue credit and cost allocation review (docket 57171) is pending before the commission without a published residential figure yet. 2026 fuel and storm cost settlement (docket 44280, 56765) takes about $4.04 a month off a typical bill from June 2026.
For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.
Other tracked projects within 25 miles
Common questions
Where is the Project Eisenhower data center?
It is in Augusta, Richmond County, GA.
Has the Project Eisenhower data center been approved?
Yes, it was approved and is now under construction.
How big is the Project Eisenhower data center?
Reported size: 140 acres, 2,150,000 square feet.