Added as filed
SpaceX Cochise County AI Data Center Campus
SpaceX (filed as Tombstone Resources LLC). Filed, 6000 MW
SpaceX confirmed at a packed and contentious community meeting on November 4, 2026 that it is behind a proposed AI data center campus filed with Cochise County under the name Tombstone Resources LLC, on about 747 acres along US Highway 191 near the Apache Generating Station and the unincorporated community of Cochise. Plans call for up to nine data center buildings using dry cooling, starting around 1,400 megawatts and growing to as much as 6,000 megawatts at full build-out, with power from Sulphur Springs Valley Electric Cooperative and a planned battery energy storage system. The Cochise County Planning and Zoning Commission has scheduled a public hearing on the special use permit for December 9, 2026 in Bisbee, after residents raised concerns about groundwater, wildlife at the nearby Willcox Playa, and noise.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when SpaceX Cochise County AI Data Center Campus changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Filed
- Operator
- SpaceX
- Applicant on record
- Tombstone Resources LLC
- Location
- Along US Highway 191 near the Apache Generating Station and the unincorporated community of Cochise, Cochise County, AZ, Cochise County, AZ
- Size
- 6000 MW, 747 acres
- Cooling
- Air cooled
- Utility
- Sulphur Springs Valley Electric Cooperative
- Next hearing
- December 9, 2026, Cochise County Planning and Zoning Commission
- First reported
- 2026-11-04
- Last updated
- November 9, 2026
What happens next
Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.
Sources
- SpaceX hosts community meeting about proposed massive data center in Cochise County, KOLD News 13, 2026-11-04
- SpaceX outlines $50 billion Cochise data center plans amid fierce opposition, Sierra Vista Herald/Review, 2026-11-05
- SpaceX Proposes Massive 747-Acre AI Data Center Near Willcox, Drawing Mixed Reactions from Rural Cochise County Residents, Gila Herald, 2026-11-05
- SpaceXAI plans data center in Arizona, Musk's firm claims it will have 6GW capacity, Data Center Dynamics, 2026-11-05
History
Common questions
Where is the SpaceX Cochise County AI data center?
It is in Cochise, Cochise County, AZ.
Has the SpaceX Cochise County AI data center been approved?
Not yet. An application has been filed and has not been decided.
How big is the SpaceX Cochise County AI data center?
Reported size: 6000 MW, 747 acres.
When is the next public hearing?
December 9, 2026, Cochise County Planning and Zoning Commission.