Salem Township Innovation Campus (Talen / AWS Susquehanna)
Amazon Web Services (filed as Talen Energy). , 1920 MW
Amazon runs a data center campus next to the Susquehanna nuclear plant near Berwick, buying up to 1,920 megawatts of carbon free power from Talen Energy through 2042. The first data center on the roughly 1,200 acre site is already operating and Talen and Amazon plan to keep expanding it toward as many as 20 buildings. It is one of three separate large data center developments now under way in Salem Township.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Salem Township Innovation Campus (Talen / AWS Susquehanna) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Operator
- Amazon Web Services
- Applicant on record
- Talen Energy
- Location
- Salem Township, Luzerne County, PA
- Size
- 1920 MW, 1200 acres
- Cooling
- Not reported
- Utility
- PPL Electric
- First reported
- 2024-03
- Last updated
- August 29, 2026
What happens next
The site is operating. A future expansion would show up here as a status change, or as a new project nearby.
Sources
- AWS acquires Talen's nuclear data center campus in Pennsylvania, Data Center Dynamics
- Talen to sell Amazon 1.9 GW from Susquehanna nuclear plant, Utility Dive, 2025-06-11
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 1920 MW facility would draw roughly 6.1 million to 21.9 million gallons of water a day, about what 70,000 households use.
PPL Electric distribution base rate case settlement raised residential rates 4.9% from July 2026: about $8 to $10 a month on a $184 bill. The order is meant to keep new data centers from pushing their power costs onto residential electric bills by requiring developers to pay for all of their own electricity. This does not change anyone's electric rate directly, but it is meant to stop the cost of new substations and power lines built for data centers from being added to everyone else's bill.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
Other tracked projects within 25 miles
Common questions
Where is the Salem Township Innovation Campus (Talen / AWS Susquehanna) data center?
It is in Salem Township, Luzerne County, PA.
How big is the Salem Township Innovation Campus (Talen / AWS Susquehanna) data center?
Reported size: 1920 MW, 1200 acres.