Is a Data Center Coming

Shackelford County, TX

Vantage Frontier Campus

Vantage Data Centers. Under construction. 1400 MW.

Vantage Data Centers is building a 1,200 acre, 1.4 GW, ten building campus called Frontier in Shackelford County near Abilene, its largest investment to date at over 25 billion dollars. The project is tied to Oracle and OpenAI Stargate capacity, with liquid cooling for high density AI racks and the first building due in the second half of 2026.

Status
Under construction
Operator
Vantage Data Centers
Applicant on record
Vantage Data Centers
Location
Albany, Shackelford County, TX (approximate, county seat)
Size
1400 MW, 1200 acres, 3,700,000 sq ft
Cooling
Closed loop (low water)
Utility
AEP Texas
First reported
2026
Last updated
August 19, 2026

Sources

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.