Is a Data Center Coming

Miami County, KS

"Project Catalyst" Data Center (Alcove Development, Osawatomie)

Alcove Development. Filed, 500 MW

Lawrence based Alcove Development signed a three year predevelopment agreement with Osawatomie for what it calls Project Catalyst, a data center campus that has grown from an initial 115 acre plan to roughly 283 acres near the Osawatomie State Hospital. The Kansas Department for Aging and Disability Services said in September 2026 that the psychiatric hospital will stay open and that it is working with the city and developer on noise and lighting mitigation, while the project's water request has dropped from 1 million to 800,000 gallons a day and its request for city supplied power has dropped from 50 to 150 megawatts down to zero. The earlier plan for industrial revenue bonds and a 50 percent, ten year property tax abatement has reportedly been removed, and the city and planning commission are still waiting on environmental and impact studies before reviewing a formal application.

How far is it from you?

Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.

Status
Filed
Operator
Not disclosed
Applicant on record
Alcove Development
Location
Osawatomie, Miami County, KS (approximate, city center)
Size
500 MW, 283 acres, 600,000 sq ft
Cooling
Not reported
Utility
Not reported
First reported
2025
Last updated
October 12, 2026

What happens next

Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 500 MW facility would draw roughly 1.6 million to 5.7 million gallons of water a day, about what 18,200 households use.

For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.

History

September 25, 2026

Added as filed

Common questions

Where is the "Project Catalyst" data center?

It is in Osawatomie, Miami County, KS.

Has the "Project Catalyst" data center been approved?

Not yet. An application has been filed and has not been decided.

How big is the "Project Catalyst" data center?

Reported size: 500 MW, 283 acres, 600,000 square feet.

Corrections and tips: use the address in the footer. We link every claim to its source.