Is a Data Center Coming

Polk County, IA

Edged Ankeny Data Center

Edged (filed as Edged Des Moines LLC). Under construction. 13 MW.

Edged is building a 187 million dollar, 13.2 megawatt data center on Ankeny's southeast side, near Southeast Four Mile Road just north of Interstate 80. The Ankeny City Council approved a development agreement with a tax increment financing incentive capped at 2 million dollars, and construction broke ground on May 6, 2025, with completion expected in 2027. The company says the facility will use closed loop, waterless cooling.

Status
Under construction
Operator
Edged
Applicant on record
Edged Des Moines LLC
Location
Ankeny, Polk County, IA
Size
13 MW, 18 acres, 105,000 sq ft
Cooling
Closed loop (low water)
Utility
MidAmerican Energy
First reported
2024
Last updated
August 29, 2026

Sources

What it would mean nearby

MidAmerican Energy is asking the commission for a 5.2% residential increase (MidAmerican Energy natural gas rate increase (docket RPU-2026-0001)). On a $58 monthly bill that is about $3 to $5 a month. This case does not set rates directly, but the new solar plant it approves will eventually be paid for through customer rates, and MidAmerican has said data center growth is a major reason it is needed.

For a noise estimate and the three distance rings, check your own address.

Follow this project

One email when Edged Ankeny Data Center changes status or a new filing lands within 25 miles of it.

Unsubscribe with one click. We do not sell the list.

Other tracked projects within 25 miles

Aureon Operator not disclosed
7.4 mi SWOperatingPolk County, IA
Microsoft Microsoft
17 mi SWOperatingDallas County, IA

Is it near you?