Is a Data Center Coming

Loudoun County, VA

Arcola Grove Rezoning

Operator not disclosed. Approved.

Loudoun County supervisors approved the Arcola Grove rezoning for a data center project near Dulles. Specific acreage and megawatt figures have not been published.

Status
Approved
Operator
Not disclosed
Location
Dulles, Loudoun County, VA (approximate, city center)
Size
MW not reported
Cooling
Not reported
Utility
Dominion Energy
Last updated
August 19, 2026

Sources

What it would mean nearby

Deferred fuel cost recovery (docket PUR-2026-00078) is pending; Dominion Energy says it would add about $7 to $9 to a typical monthly bill. Data center cost allocation and transmission rider (docket PUR-2026-00056) adds about $0.94 a month to a typical bill, decided August 1, 2026. 2025 biennial review base rate increase (docket PUR-2025-00058) adds about $11.24 a month to a typical bill from January 2026.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

Amazon IAD62 Amazon Web Services
1.0 mi EOperatingLoudoun County, VA
Amazon IAD125 Amazon Web Services
1.2 mi WOperatingLoudoun County, VA

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.