AWS Calvert Technology Center (Calvert Cliffs)
Amazon Web Services (filed as Amazon Data Services Inc.). Withdrawn, 500 MW
Amazon Web Services revealed plans in April 2026 to build the Calvert Technology Center, a set of seven data center buildings across three campuses totaling about 2.4 million square feet and up to 500 megawatts, next to the Calvert Cliffs nuclear power plant in Lusby, and submitted a Conceptual Site Development Plan application in May 2026. After voters in the June 23, 2026 primary ousted all three sitting county commissioners who had opposed a pause on data center development, Amazon formally withdrew its Calvert Technology Center application, with Calvert County government announcing the withdrawal on August 4, 2026.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when AWS Calvert Technology Center (Calvert Cliffs) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Withdrawn
- Operator
- Amazon Web Services
- Applicant on record
- Amazon Data Services Inc.
- Location
- Lusby, Calvert County, MD (approximate, city center)
- Size
- 500 MW, 2,400,000 sq ft
- Cooling
- Not reported
- Utility
- Southern Maryland Electric Cooperative
- First reported
- 2026-04
- Last updated
- September 24, 2026
What happens next
This proposal will not move forward as filed, but the land it was proposed on can be proposed again under a new project. See other stopped projects.
Sources
- Amazon abandons plans for data center campus at Calvert Cliffs, Maryland Matters, 2026-08-04
- Amazon abandons plans for data center campus at Md.'s Calvert Cliffs nuclear plant, WTOP, 2026-08-05
- AWS proposes data center campus next to nuclear plant in Calvert County, Maryland, Data Center Dynamics
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 500 MW facility would draw roughly 1.6 million to 5.7 million gallons of water a day, about what 18,200 households use.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
History
Common questions
Where is the AWS Calvert Technology Center (Calvert Cliffs) data center?
It is in Lusby, Calvert County, MD.
Has the AWS Calvert Technology Center (Calvert Cliffs) data center been approved?
No. The developer withdrew the proposal.
How big is the AWS Calvert Technology Center (Calvert Cliffs) data center?
Reported size: 500 MW, 2,400,000 square feet.