Amazon Web Services. Under construction.

AWS is building a mega campus of AI data centers on more than 1,000 acres of former farmland near New Carlisle, about 15 miles west of South Bend. As of July 2026 AWS has invested 13.8 billion dollars, exceeding its original 11 billion dollar commitment, with about 18 of a planned 30 buildings operational and construction continuing.

Status
Under construction
Operator
Amazon Web Services
Applicant on record
Amazon Web Services
Location
New Carlisle, St. Joseph County, IN (approximate, city center)
Size
MW not reported, 1000 acres
Cooling
Not reported
Utility
Indiana Michigan Power
First reported
2024-04-25
Last updated
August 19, 2026

What happens next

The site is under construction. The next step is opening.

Sources

What it would mean nearby

This deal is meant to keep the cost of new substations and transmission lines for AWS's data centers off the bills of regular I&M customers by making the data center pay for capacity it reserves, not just power it actually uses.

For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.

Other tracked projects within 25 miles

Common questions

Where is the AWS New Carlisle data center?

It is in New Carlisle, St. Joseph County, IN.

Has the AWS New Carlisle data center been approved?

Yes, it was approved and is now under construction.

How big is the AWS New Carlisle data center?

Reported size: 1000 acres.

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.