Prime Storage Delk Road Data Center
Prime Storage. Approved. 18 MW.
An 18 megawatt data center proposed to occupy about 21,570 square feet (roughly 22 percent) of an existing 90,000 square foot Prime Storage self-storage building on Powers Ferry Place off Delk Road in Marietta, Cobb County, on a 10.7 acre site facing Interstate 75. The Marietta Planning Commission recommended approval 4-3 in June 2026 and the City Council approved it 5-2 on August 13, 2026, with conditions including an independent sound study, noise monitoring, generator silencing, and a covenant barring Prime Storage from adding data centers at its other Marietta facilities. It is described as serving local law enforcement, medical, emergency and business needs.
Follow this project
One free email when Prime Storage Delk Road Data Center changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get an address report.
- Status
- Approved
- Operator
- Prime Storage
- Applicant on record
- Prime Storage
- Location
- Powers Ferry Place, off Delk Road near Interstate 75, Marietta, Cobb County, GA
- Size
- 18 MW, 11 acres, 21,570 sq ft
- Cooling
- Not reported
- Utility
- Georgia Power
- Last updated
- August 13, 2026
What happens next
Still to come: permits and construction. Builders do not always announce a construction start date in advance.
Sources
- Marietta to hear data center proposal off Delk Road, East Cobb News, 2026-07-02
- Marietta City Council approves data center off Delk Road, East Cobb News, 2026-08-13
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 18 MW facility would draw roughly 57,000 to 205,000 gallons of water a day, about what 700 households use.
Base rate freeze through 2028 (docket 44280) holds base rates flat from July 2025. Fuel and storm riders are separate and can still move. Real-time pricing revenue credit and cost allocation review (docket 57171) is pending before the commission without a published residential figure yet. 2026 fuel and storm cost settlement (docket 44280, 56765) takes about $4.04 a month off a typical bill from June 2026.
For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.
Other tracked projects within 25 miles
Common questions
Where is the Prime Storage Delk Road data center?
It is in Marietta, Cobb County, GA.
Has the Prime Storage Delk Road data center been approved?
Yes, it has been approved.
How big is the Prime Storage Delk Road data center?
Reported size: 18 MW, 11 acres, 21,570 square feet.
Is it near you?
Corrections and tips: use the address in the footer. We link every claim to its source.