EdgeConneX. Denied.

EdgeConneX proposed a six building, 4.4 million square foot data center campus with a utility substation on about 700 acres near the Interstate 20 and Liberty Road area of western Douglas County, close to Villa Rica. After a packed public hearing where the project size drew audible jeers from residents, Douglas County commissioners voted 4-1 on July 7, 2026 to deny the rezoning request, the second time in about seven months that county leaders rejected a large data center proposal on this same property.

Status
Denied
Operator
EdgeConneX
Applicant on record
EdgeConneX
Location
near Interstate 20 and Liberty Road, western Douglas County, Villa Rica, Douglas County, GA
Size
MW not reported, 700 acres, 4,400,000 sq ft
Cooling
Not reported
Utility
Not reported
Last updated
July 7, 2026

Sources

What it would mean nearby

Oglethorpe Power, which generates most of the electricity Georgia's EMCs sell, is adding natural gas plants it ties to data center and industrial load. EMC rates are set by each cooperative's board, not the Public Service Commission, so watch your EMC's rate notices.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

Project Sail Prologis
18 mi SApproved 900 MW Coweta County, GA

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.