Google Papillion Data Center, Building 6
Google. Filed, 57 MW
Google is planning a sixth building at its Papillion, Sarpy County data center campus, adding about 57 megawatts of capacity with an expected 2027 completion, according to industry tracker Cleanview. The addition continues Google's build out in the Omaha metro area, where the company already operates multiple facilities in Douglas and Sarpy counties, and comes as Meta separately expands its own nearby Papillion campus. Google's own Nebraska locations page confirms an active presence in the state but does not break out individual building level detail.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Google Papillion Data Center, Building 6 changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Filed
- Operator
- Applicant on record
- Location
- Papillion, Sarpy County, NE (approximate, city center)
- Size
- 57 MW
- Cooling
- Not reported
- Utility
- Omaha Public Power District
- Last updated
- September 24, 2026
What happens next
Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.
Sources
- Nebraska, USA - Google Data Center Location, Google
- Data Centers in Nebraska - Project List & Locations, Cleanview
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 57 MW facility would draw roughly 181,000 to 650,000 gallons of water a day, about what 2,100 households use.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
History
Other tracked projects within 25 miles
Common questions
Where is the Google Papillion Data Center, Building 6?
It is in Papillion, Sarpy County, NE.
Has the Google Papillion Data Center, Building 6 been approved?
Not yet. An application has been filed and has not been decided.
How big is the Google Papillion Data Center, Building 6?
Reported size: 57 MW.