Meta Sarpy Data Center Expansion

Meta. Filed.

Meta is expanding its already operating Sarpy County data center campus in Papillion to nine buildings and about 4 million square feet. The original Papillion site was announced in 2017, grew to six buildings by 2018, went live in 2019, and has been expanded multiple times since, most recently with a further 1 million square feet and 400 million dollars in added investment. The campus is one of Meta's largest US data center clusters and continues to grow alongside a competing Google campus in the same city.

Status
Filed
Operator
Meta
Applicant on record
Meta
Location
Papillion, Sarpy County, NE (approximate, city center)
Size
MW not reported, 4,000,000 sq ft
Cooling
Not reported
Utility
Omaha Public Power District
First reported
2026
Last updated
September 24, 2026

What happens next

Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.

Sources

History

September 25, 2026

Added as filed

Other tracked projects within 25 miles

Fidelity Fidelity
2.3 mi WOperatingSarpy County, NE
Yahoo Yahoo
2.9 mi NWOperatingSarpy County, NE
Google Google
5.6 mi WOperatingSarpy County, NE

Common questions

Where is the Meta Sarpy Data Center Expansion?

It is in Papillion, Sarpy County, NE.

Has the Meta Sarpy Data Center Expansion been approved?

Not yet. An application has been filed and has not been decided.

How big is the Meta Sarpy Data Center Expansion?

Reported size: 4,000,000 square feet.

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.