Auburndale Technology Center (Hillwood / Pace Road DC Development)
Pace Road DC Development, LLC (Hillwood Development Company). Filed, 700 MW
Texas based Hillwood Development, through an entity called Pace Road DC Development LLC, bought a roughly 75 acre industrial property at 810 and 820 Pace Road in Auburndale in December 2025 and plans to convert the existing warehouse buildings into a data center called the Auburndale Technology Center. The company filed a building permit application in August 2026 and a site plan in early November 2026, targeting about 350 megawatts of Tampa Electric Company power in a first phase with closed loop water cooling, and up to 700 megawatts and two more buildings in a later phase expected online by 2029. The Auburndale City Commission held that special public workshop on November 10, 2026, drawing roughly 500 residents who raised power, water, noise, and property value concerns, but because the site is privately owned the project proceeds through administrative permit review rather than a commission vote, and no operator has been publicly confirmed for the facility.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Auburndale Technology Center (Hillwood / Pace Road DC Development) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Filed
- Operator
- Not disclosed
- Applicant on record
- Pace Road DC Development, LLC (Hillwood Development Company)
- Location
- 810-820 Pace Road, Auburndale, FL, Polk County, FL
- Size
- 700 MW, 75 acres
- Cooling
- Closed loop (low water)
- Utility
- Tampa Electric Company
- First reported
- 2026-08
- Last updated
- November 16, 2026
What happens next
Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.
Sources
- Auburndale could be getting a major data center: Here's what we know, WTVT / Tampa Bay 28
- Major data center planned for Polk County: What to know, WFLA
- Proposed Auburndale data center draws scrutiny over power demand, water use and impact, FOX 13 News, 2026-11-10
History
Added as filed
Common questions
Where is the Auburndale Technology Center (Hillwood / Pace Road DC Development) data center?
It is in Auburndale, Polk County, FL.
Has the Auburndale Technology Center (Hillwood / Pace Road DC Development) data center been approved?
Not yet. An application has been filed and has not been decided.
How big is the Auburndale Technology Center (Hillwood / Pace Road DC Development) data center?
Reported size: 700 MW, 75 acres.