Henrico County approved the 622-acre Hourigan rezoning for data center development in May 2024. The tract includes portions of two Civil War battlefield sites, which drew preservation concerns during review.

Status
Approved
Operator
Not disclosed
Applicant on record
Hourigan
Location
Henrico, Henrico County, VA (approximate, county seat)
Size
MW not reported, 622 acres
Cooling
Not reported
Utility
Dominion Energy
Last updated
May 1, 2024

Sources

What it would mean nearby

Deferred fuel cost recovery (docket PUR-2026-00078) is pending; Dominion Energy says it would add about $7 to $9 to a typical monthly bill. Data center cost allocation and transmission rider (docket PUR-2026-00056) adds about $0.94 a month to a typical bill, decided August 1, 2026. 2025 biennial review base rate increase (docket PUR-2025-00058) adds about $11.24 a month to a typical bill from January 2026.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.