Nebius Group (filed as DataOne (a division of BSO)). Under construction. 300 MW.

Nebius Group, a Netherlands based AI infrastructure company with a reported 17 billion dollar computing supply deal with Microsoft, is building a 2.6 million square foot campus of six buildings in Vineland with DataOne handling construction, aiming for up to 300 megawatts of capacity in phases. As of September 2026 the site is under construction but has drawn two city stop work orders, a withdrawn state air permit application, and reports that dozens of backup generators had been running without permits. Nearby residents have also complained about a persistent humming noise from the site.

Status
Under construction
Operator
Nebius Group
Applicant on record
DataOne (a division of BSO)
Location
3963 S Lincoln Ave, Vineland, NJ 08361, Cumberland County, NJ
Size
300 MW, 2,600,000 sq ft
Cooling
Not reported
Utility
South Jersey Industries / Atlantic City Electric
First reported
2026-07
Last updated
September 24, 2026

What happens next

The site is under construction. The next step is opening.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 300 MW facility would draw roughly 951,000 to 3.4 million gallons of water a day, about what 10,900 households use.

For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.

History

September 25, 2026

Added as under construction

Common questions

Where is the Nebius / DataOne Vineland data center?

It is in Vineland, Cumberland County, NJ.

Has the Nebius / DataOne Vineland data center been approved?

Yes, it was approved and is now under construction.

How big is the Nebius / DataOne Vineland data center?

Reported size: 300 MW, 2,600,000 square feet.

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.