T5 Data Centers (filed as Oppidan). Under construction. 10 MW.

Minnesota developer Oppidan, with operator T5 Data Centers, is building a 90,000 square foot, 10 megawatt data center southwest of K-10 and K-7 in Olathe, between Honeywell Aerospace and a church, after the city approved the project in 2024. Unlike some of its neighbors, Olathe has generally steered away from hosting large hyperscale campuses directly, instead courting industrial revenue bonds for the factories that build electrical infrastructure and switchgear for the wider Kansas City area data center boom.

Status
Under construction
Operator
T5 Data Centers
Applicant on record
Oppidan
Location
Olathe, Johnson County, KS (approximate, city center)
Size
10 MW, 90,000 sq ft
Cooling
Not reported
Utility
Evergy
First reported
2024
Last updated
September 24, 2026

What happens next

The site is under construction. The next step is opening.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 10 MW facility would draw roughly 32,000 to 114,000 gallons of water a day, about what 400 households use.

For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.

History

September 25, 2026

Added as under construction

Other tracked projects within 25 miles

Common questions

Where is the Olathe data center?

It is in Olathe, Johnson County, KS.

Has the Olathe data center been approved?

Yes, it was approved and is now under construction.

How big is the Olathe data center?

Reported size: 10 MW, 90,000 square feet.

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.