Is a Data Center Coming

Jefferson County, AL

Project Marvel (QTS Bessemer)

QTS Data Centers (filed as Logistics Land Investment LLC). Approved. 1200 MW.

Known as Project Marvel, this QTS data center would occupy more than 1,600 acres on the edge of Bessemer with up to 1,200 megawatts and 4.5 million square feet, reported at up to 14.5 billion dollars. The city council approved rezoning despite the project being kept largely secret, and a nondisclosure agreement requiring officials to destroy records drew a lawsuit threat and broad opposition.

Status
Approved
Operator
QTS Data Centers
Applicant on record
Logistics Land Investment LLC
Location
southwest edge of Bessemer, AL, Jefferson County, AL (approximate, city center)
Size
1200 MW, 1600 acres, 4,500,000 sq ft
Cooling
Not reported
Utility
Alabama Power
First reported
2025-11
Last updated
August 19, 2026

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 1200 MW facility would draw roughly 3.8 million to 13.7 million gallons of water a day, about what 43,700 households use.

Alabama Power RSE rate freeze holds base rates flat, decided December 8, 2025. Fuel and storm riders are separate and can still move.

For a noise estimate and the three distance rings, check your own address.