Is a Data Center Coming

Jefferson County, AL

Project Marvel (QTS Bessemer)

QTS Data Centers (filed as Logistics Land Investment LLC). Approved, 1200 MW

Known as Project Marvel, this QTS data center would occupy more than 1,600 acres on the edge of Bessemer with up to 1,200 megawatts and 4.5 million square feet, reported at up to 14.5 billion dollars. The city council approved rezoning despite the project being kept largely secret, and a nondisclosure agreement requiring officials to destroy records drew a lawsuit threat and broad opposition.

How far is it from you?

Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.

Status
Approved
Operator
QTS Data Centers
Applicant on record
Logistics Land Investment LLC
Location
southwest edge of Bessemer, AL, Jefferson County, AL (approximate, city center)
Size
1200 MW, 1600 acres, 4,500,000 sq ft
Cooling
Not reported
Utility
Alabama Power
First reported
2025-11
Last updated
August 19, 2026

What happens next

Still to come: permits and construction. Builders do not always announce a construction start date in advance.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 1200 MW facility would draw roughly 3.8 million to 13.7 million gallons of water a day, about what 43,700 households use.

Alabama Power RSE rate freeze holds base rates flat, decided December 8, 2025. Fuel and storm riders are separate and can still move. This does not change any household's bill directly. It sets rules for how Alabama Power's contracts with big data centers must be reviewed and billed, aimed at making sure those customers pay their own costs instead of spreading them to everyone else, though key financial details in the contracts are still kept confidential.

For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.

Other tracked projects within 25 miles

Common questions

Where is the Project Marvel (QTS Bessemer) data center?

It is in Bessemer, Jefferson County, AL.

Has the Project Marvel (QTS Bessemer) data center been approved?

Yes, it has been approved.

How big is the Project Marvel (QTS Bessemer) data center?

Reported size: 1200 MW, 1600 acres, 4,500,000 square feet.

Corrections and tips: use the address in the footer. We link every claim to its source.