Added as under construction
Percheron Data Center (Rowan Digital Infrastructure)
Rowan Digital Infrastructure (filed as Rowan Green Data LLC). Under construction, 300 MW
Rowan Digital Infrastructure, backed by Houston investor Quinbrook, is building the Percheron data center campus on 274 acres of former Threemile Canyon Farms land about 11 miles southwest of Boardman, on ground the developer describes as poor quality farmland that has sat vacant for decades. Morrow County commissioners unanimously approved the rezoning in September 2023, and Rowan broke ground on the first 300 megawatt phase in January 2026, targeting delivery by late 2027. The developer says the campus will be powered entirely by renewable energy bought through Pacific Power and will use minimal, recycled water piped in by the Port of Morrow.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Percheron Data Center (Rowan Digital Infrastructure) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Under construction
- Operator
- Rowan Digital Infrastructure
- Applicant on record
- Rowan Green Data LLC
- Location
- Boardman, Morrow County, OR (approximate, city center)
- Size
- 300 MW, 274 acres, 1,125,000 sq ft
- Cooling
- Not reported
- Utility
- Pacific Power
- First reported
- 2023-09
- Last updated
- September 24, 2026
What happens next
The site is under construction. The next step is opening.
Sources
- FAQs, Percheron Data Center, Rowan Digital Infrastructure
- Quinbrook's Rowan planning 1 million sq ft data center campus in Morrow County, Oregon, Data Center Dynamics
- Morrow County commissioners consider new data center, La Grande Observer, 2023-08-10
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 300 MW facility would draw roughly 951,000 to 3.4 million gallons of water a day, about what 10,900 households use.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
History
Other tracked projects within 25 miles
Common questions
Where is the Percheron data center?
It is in Boardman, Morrow County, OR.
Has the Percheron data center been approved?
Yes, it was approved and is now under construction.
How big is the Percheron data center?
Reported size: 300 MW, 274 acres, 1,125,000 square feet.