Is a Data Center Coming

Fulton County, GA

Stonewall Tell Data Center (RSC)

RSC Investment Management LLC. Filed.

RSC Investment Management LLC filed a Development of Regional Impact application in December 2024 for a 1.9 million square foot data center campus on 59 acres south of South Fulton Parkway and east of Stonewall Tell Road in Union City, near existing Microsoft and Vantage data center sites. It was reported as the seventh large data center proposal in south Fulton County that year. No confirmed end user or hearing outcome had been reported as of mid 2026.

Status
Filed
Operator
Not disclosed
Applicant on record
RSC Investment Management LLC
Location
south of South Fulton Parkway, east of Stonewall Tell Road, Union City, Fulton County, GA
Size
MW not reported, 59 acres, 1,900,000 sq ft
Cooling
Not reported
Utility
Not reported
First reported
2024-12-10
Last updated
December 10, 2024

Sources

What it would mean nearby

Base rate freeze through 2028 (docket 44280) holds base rates flat from July 2025. Fuel and storm riders are separate and can still move. 2026 fuel and storm cost settlement (docket 44280, 56765) takes about $4.04 a month off a typical bill from June 2026. The December 2025 certification of about 9,885 MW of new generation for data center load came with a promise of at least $8.50 a month of downward pressure on a typical bill in 2029 through 2031, because large customers are meant to carry more of the cost. Consumer groups warned it could instead add around $20 a month if the projected data center demand does not show up.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.