Sentinel / Green Fig Data Center
Green Fig. On hold
Green Fig's 1.5 million square foot data center on Swedesford Road, on part of the old Foote Mineral Company Superfund site, was approved in 2024 after the developer scrapped a larger 1.7 million square foot version amid heavy public opposition. The township has since issued more than one stop work order, most recently in August 2026, after the developer could not show that the local water utility, Aqua, had committed enough water for the project. Neighbors have also raised concerns about whether the old industrial contamination on the site has been fully cleaned up.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Sentinel / Green Fig Data Center changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- On hold
- Operator
- Not disclosed
- Applicant on record
- Green Fig
- Location
- Swedesford Road, East Whiteland Township, PA, Chester County, PA
- Size
- MW not reported, 1,500,000 sq ft
- Cooling
- Not reported
- Utility
- PECO
- Last updated
- August 29, 2026
What happens next
Paused by the developer, a regulator, or a court. It could resume, be withdrawn, or be replaced by a new filing on the same land.
Sources
- The controversial East Whiteland data center project has been issued its second stop work order, The Philadelphia Inquirer, 2026-08-27
- East Whiteland, PA Data Center Developer Withdraws Application After Fierce Public Opposition, Food & Water Watch, 2026-05-05
What it would mean nearby
PECO price to compare increase June 2026 raised residential rates 5% from June 2026: about $7 to $9 a month on a $160 bill. The order is meant to keep new data centers from pushing their power costs onto residential electric bills by requiring developers to pay for all of their own electricity. This does not change anyone's electric rate directly, but it is meant to stop the cost of new substations and power lines built for data centers from being added to everyone else's bill.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
Other tracked projects within 25 miles
Common questions
Where is the Sentinel / Green Fig data center?
It is in East Whiteland Township, Chester County, PA.
Has the Sentinel / Green Fig data center been approved?
Not yet. It is on hold.
How big is the Sentinel / Green Fig data center?
Reported size: 1,500,000 square feet.