Serverfarm. Under construction.

Serverfarm is expanding its Houston footprint with CTX2, a planned 438,000 square foot facility at 15555 Cutten Road adjacent to its existing data centers, part of a 137 million dollar expansion designed by HKS with construction running from mid 2025 to mid 2026.

Status
Under construction
Operator
Serverfarm
Applicant on record
Serverfarm
Location
15555 Cutten Road, Houston, TX, Harris County, TX
Size
MW not reported, 438,000 sq ft
Cooling
Not reported
Utility
CenterPoint Energy
First reported
2025
Last updated
August 19, 2026

Sources

What it would mean nearby

Storm cost recovery (Beryl and 2024-25 storms) adds about $2.00 a month to a typical bill, decided October 2, 2025. 2024 Houston Electric rate case takes about $1.00 a month off a typical bill, decided March 13, 2025.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.