Status: approved to under construction
T5 @ Chicago IV Data Center Campus
T5 Data Centers. Under construction, 1550 MW
T5 Data Centers' Chicago IV campus in Grayslake is approved for up to 472 acres and over 10 million square feet, drawing roughly 1.55 gigawatts from ComEd. The village issued its first building permit around September 1, 2026, allowing site work to begin on the initial 800,000 square foot building even as construction proceeds. Nine residents and the Preservation of Community Well-being Collective LLC sued the village, T5, and Alter Asset Management on July 31, 2026 seeking to void the project's approvals and block further permits, and an initial status hearing in that case is confirmed for 9 a.m. October 30, 2026 in Lake County Circuit Court.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when T5 @ Chicago IV Data Center Campus changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Under construction
- Operator
- T5 Data Centers
- Applicant on record
- T5 Data Centers
- Location
- Grayslake, Lake County, IL
- Size
- 1550 MW, 472 acres, 10,000,000 sq ft
- Cooling
- Not reported
- Utility
- ComEd
- Next hearing
- October 30, 2026, Lake County Circuit Court (lawsuit status hearing)
- First reported
- 2024-09
- Last updated
- October 12, 2026
What happens next
The site is under construction. The next step is opening.
Sources
- Grayslake issues first permit for construction to begin on mega data center campus as lawsuit seeks to block development, Lake & McHenry County Scanner, 2026-09-01
- Project of unprecedented scale: Lake County residents file lawsuit to block 472-acre data center campus in Grayslake, Lake & McHenry County Scanner, 2026-08-08
- Grayslake, T5 moving forward with data center development in the midst of resident lawsuit, The Real Deal, 2026-09-01
- Critics of Grayslake data center plan sue to stop construction, Daily Herald, 2026-08-07
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 1550 MW facility would draw roughly 4.9 million to 17.7 million gallons of water a day, about what 56,500 households use.
This case does not change what a household pays today, but it is the main tool Illinois regulators are using to try to stop the cost of new grid equipment for data centers from landing on residential bills. ComEd annual reconciliation rate case (docket 25-0383) adds about $3.10 a month to a typical bill from January 2026. PJM capacity auction price spike hits ComEd supply charges adds about $10.50 a month to a typical bill from June 2025.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
History
Other tracked projects within 25 miles
Common questions
Where is the T5 @ Chicago IV data center?
It is in Grayslake, Lake County, IL.
Has the T5 @ Chicago IV data center been approved?
Yes, it was approved and is now under construction.
How big is the T5 @ Chicago IV data center?
Reported size: 1550 MW, 472 acres, 10,000,000 square feet.
When is the next public hearing?
October 30, 2026, Lake County Circuit Court (lawsuit status hearing).
Corrections and tips: use the address in the footer. We link every claim to its source.