Goochland County, VA
Tuckahoe Technology Park
Tract. Filed. 900 MW.
Denver-based Tract filed a pre-application in June 2026 for a 900 megawatt, 871-acre data center campus along Patterson Avenue in eastern Goochland County, the first project proposed under the county's new Technology Overlay District. It borders the Mosaic 55-plus community and has drawn organized resident opposition.
- Status
- Filed
- Operator
- Not disclosed
- Applicant on record
- Tract
- Location
- along Route 6/Patterson Avenue, Goochland, Goochland County, VA
- Size
- 900 MW, 871 acres
- Cooling
- Not reported
- Utility
- Dominion Energy
- First reported
- 2026-06-10
- Last updated
- July 27, 2026
Sources
- Goochland residents rebuff data center developer Tract ahead of permit application, Virginia Mercury, 2026-07-27
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 900 MW facility would draw roughly 2.9 million to 10.3 million gallons of water a day, about what 32,800 households use.
Deferred fuel cost recovery (docket PUR-2026-00078) is pending; Dominion Energy says it would add about $7 to $9 to a typical monthly bill. Data center cost allocation and transmission rider (docket PUR-2026-00056) adds about $0.94 a month to a typical bill, decided August 1, 2026. 2025 biennial review base rate increase (docket PUR-2025-00058) adds about $11.24 a month to a typical bill from January 2026.
For a noise estimate and the three distance rings, check your own address.
Other tracked projects within 25 miles
Is it near you?
Corrections and tips: use the address in the footer. We link every claim to its source.