Denver-based Tract filed a pre-application in June 2026 for a 900 megawatt, 871-acre data center campus along Patterson Avenue in eastern Goochland County, the first project proposed under the county's new Technology Overlay District. It borders the Mosaic 55-plus community and has drawn organized resident opposition.

Status
Filed
Operator
Not disclosed
Applicant on record
Tract
Location
along Route 6/Patterson Avenue, Goochland, Goochland County, VA
Size
900 MW, 871 acres
Cooling
Not reported
Utility
Dominion Energy
First reported
2026-06-10
Last updated
July 27, 2026

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 900 MW facility would draw roughly 2.9 million to 10.3 million gallons of water a day, about what 32,800 households use.

Deferred fuel cost recovery (docket PUR-2026-00078) is pending; Dominion Energy says it would add about $7 to $9 to a typical monthly bill. Data center cost allocation and transmission rider (docket PUR-2026-00056) adds about $0.94 a month to a typical bill, decided August 1, 2026. 2025 biennial review base rate increase (docket PUR-2025-00058) adds about $11.24 a month to a typical bill from January 2026.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.