Hearing removed (was September 14, 2026)
"Project Flex" Data Center (Verrus, Lyon Township)
Verrus. Filed
Verrus wants to build a six building, 1.8 million square foot data center called Project Flex on 172 acres off Milford Road in Lyon Township, near South Lyon. The township's planning commission conditionally approved the project in September 2025, valid only until September 2027, and Verrus submitted revised plans on August 13, 2026 addressing noise, lighting, and stormwater concerns with taller acoustic walls and relocated transmission lines. The township has since pulled the project from its September 14, 2026 planning commission agenda and no new hearing date has been announced.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when "Project Flex" Data Center (Verrus, Lyon Township) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Filed
- Operator
- Verrus
- Applicant on record
- Verrus
- Location
- Lyon Township, Oakland County, MI (approximate, city center)
- Size
- MW not reported, 172 acres, 1,800,000 sq ft
- Cooling
- Not reported
- Utility
- DTE Electric
- Last updated
- September 14, 2026
What happens next
Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.
Sources
- Verrus data center planned for Lyon Township, Crain's Detroit Business
- Lyon Township 'may be revisiting' data center site plan: Residents pack meeting, Planet Detroit, 2026-01-13
- Project Flex data center eyes final Lyon Township approval amid pushback from nearby residents, WXYZ
- Project Flex Developer to Go Back Before Lyon Township Planners in September, WHMI 93.5, 2026-08
- Project Flex one year later: Part I, The Livingston Post
What it would mean nearby
DTE Electric is asking the commission for a 9.7% residential increase (2027 electric rate case (docket U-22046)). On a $160 monthly bill that is about $13 to $18 a month. 2026 electric distribution rate case (docket U-21860) raised residential rates 4.1% from March 2026: about $6 to $8 a month on a $160 bill. The order is meant to keep this one data center's power costs off the bills of regular DTE residential customers, but critics argue the fast, largely ex parte approval process did not fully test that promise.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
History
Other tracked projects within 25 miles
Common questions
Where is the "Project Flex" data center?
It is in Lyon Township, Oakland County, MI.
Has the "Project Flex" data center been approved?
Not yet. An application has been filed and has not been decided.
How big is the "Project Flex" data center?
Reported size: 172 acres, 1,800,000 square feet.
Corrections and tips: use the address in the footer. We link every claim to its source.