Stack Infrastructure Berry Hill Megasite Stack Infrastructure
Pittsylvania County, VA
Anchorstone SOVA Route 58 East Campus
Anchorstone Advisors LLC. Approved. 200 MW.
Pittsylvania County's board approved a rezoning of 946 acres off Route 58 East in Ringgold for a data center campus with an initial 200 megawatts of capacity, with potential for significant future expansion and an estimated investment up to 5 billion dollars.
- Status
- Approved
- Operator
- Not disclosed
- Applicant on record
- Anchorstone Advisors LLC
- Location
- off US Route 58 East, Ringgold, Pittsylvania County, VA (approximate, city center)
- Size
- 200 MW, 946 acres
- Cooling
- Not reported
- Utility
- Not reported
- Last updated
- August 19, 2026
Sources
- Land and Expand: Virginia Data Centers, Data Center Frontier
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 200 MW facility would draw roughly 634,000 to 2.3 million gallons of water a day, about what 7,300 households use.
For a noise estimate and the three distance rings, check your own address.
Other tracked projects within 25 miles
Microsoft Person County Data Center Microsoft
Is it near you?
Corrections and tips: use the address in the footer. We link every claim to its source.