AVAIO Digital Partners. Approved. 150 MW.

AVAIO Digital Partners announced Avaio Digital Leo, a 760 acre AI ready data center and power campus off Interstate 530 in Pulaski County, described as the largest economic investment in Arkansas history. The first phase carries a 6 billion dollar price tag with construction scheduled to begin in early 2026 and initial operation by June 2027, and the company says full buildout could exceed 21 billion dollars and grow power demand from an initial 150 megawatts contracted with Entergy Arkansas to as much as 1 gigawatt. The project is expected to create more than 500 permanent jobs over five years plus thousands of construction jobs.

Status
Approved
Operator
AVAIO Digital Partners
Applicant on record
AVAIO Digital Partners
Location
Little Rock, Pulaski County, AR (approximate, city center)
Size
150 MW, 760 acres
Cooling
Not reported
Utility
Entergy Arkansas
First reported
2026-01-12
Last updated
September 24, 2026

What happens next

Still to come: permits and construction. Builders do not always announce a construction start date in advance.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 150 MW facility would draw roughly 476,000 to 1.7 million gallons of water a day, about what 5,500 households use.

For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.

History

September 25, 2026

Added as approved

Other tracked projects within 25 miles

Common questions

Where is the Avaio Digital Leo data center?

It is in Little Rock, Pulaski County, AR.

Has the Avaio Digital Leo data center been approved?

Yes, it has been approved.

How big is the Avaio Digital Leo data center?

Reported size: 150 MW, 760 acres.

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.