Is a Data Center Coming

Portage County, OH

Bitdeer Shalersville Data Center Proposal

Bitdeer Technologies Group. Filed. 750 MW.

Bitdeer Technologies Group, a Singapore based bitcoin mining and AI infrastructure firm, is proposing a data center in Shalersville Township targeting up to 750 megawatts of power capacity. A May 29 developer open house drew a standing room only crowd, and Shalersville Township trustees have since proposed a zoning code change that could effectively keep the project out of the township.

Status
Filed
Operator
Bitdeer Technologies Group
Applicant on record
Bitdeer Technologies Group
Location
Shalersville, Portage County, OH (approximate, city center)
Size
750 MW
Cooling
Not reported
Utility
Not reported
First reported
2026-06
Last updated
August 19, 2026

What happens next

Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 750 MW facility would draw roughly 2.4 million to 8.6 million gallons of water a day, about what 27,300 households use.

For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.

Other tracked projects within 25 miles

Involta-Akron Operator not disclosed
20 mi SWOperatingSummit County, OH

Common questions

Where is the Bitdeer Shalersville data center?

It is in Shalersville, Portage County, OH.

Has the Bitdeer Shalersville data center been approved?

Not yet. An application has been filed and has not been decided.

How big is the Bitdeer Shalersville data center?

Reported size: 750 MW.

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.