Cielo Digital Infrastructure Campus
Cielo Digital Infrastructure LLC (Arroyo Investors). Approved. 240 MW.
Culpeper supervisors approved rezoning of four parcels totaling more than 120 acres along James Madison Highway for up to 2.4 million square feet of data centers with at least 240 megawatts of capacity, on a 7-2 vote in December 2023.
Follow this project
One free email when Cielo Digital Infrastructure Campus changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get an address report.
- Status
- Approved
- Operator
- Not disclosed
- Applicant on record
- Cielo Digital Infrastructure LLC (Arroyo Investors)
- Location
- Route 15/29 (James Madison Highway), Stevensburg, Culpeper County, VA (approximate, city center)
- Size
- 240 MW, 120 acres, 2,400,000 sq ft
- Cooling
- Not reported
- Utility
- Not reported
- Last updated
- December 5, 2023
What happens next
Still to come: permits and construction. Builders do not always announce a construction start date in advance.
Sources
- Culpeper County approves data center rezoning on James Madison Highway, InsideNoVa, 2023-12-05
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 240 MW facility would draw roughly 761,000 to 2.7 million gallons of water a day, about what 8,700 households use.
For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.
Other tracked projects within 25 miles
Common questions
Where is the Cielo Digital Infrastructure Campus data center?
It is in Stevensburg, Culpeper County, VA.
Has the Cielo Digital Infrastructure Campus data center been approved?
Yes, it has been approved.
How big is the Cielo Digital Infrastructure Campus data center?
Reported size: 240 MW, 120 acres, 2,400,000 square feet.