Fauquier County, VA
Remington Technology Park
PointOne Holdings Inc.. On hold. 600 MW.
Remington Technology Park was rezoned for up to six data centers on 234 acres back in 2018, but construction has been delayed for years by lack of available power. In 2026 the county approved an on-site natural gas fuel cell plant to help power the site while it waits on grid capacity.
- Status
- On hold
- Operator
- Not disclosed
- Applicant on record
- PointOne Holdings Inc.
- Location
- Lucky Hill Road, Remington, Fauquier County, VA (approximate, city center)
- Size
- 600 MW, 234 acres, 1,800,000 sq ft
- Cooling
- Not reported
- Utility
- Dominion Energy
- First reported
- 2018-03
- Last updated
- June 20, 2026
Sources
- Fauquier Board of Supervisors approves private power plant for Remington Technology Park data center, Fauquier Now
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 600 MW facility would draw roughly 1.9 million to 6.8 million gallons of water a day, about what 21,900 households use.
Deferred fuel cost recovery (docket PUR-2026-00078) is pending; Dominion Energy says it would add about $7 to $9 to a typical monthly bill. Data center cost allocation and transmission rider (docket PUR-2026-00056) adds about $0.94 a month to a typical bill, decided August 1, 2026. 2025 biennial review base rate increase (docket PUR-2025-00058) adds about $11.24 a month to a typical bill from January 2026.
For a noise estimate and the three distance rings, check your own address.