Crossroads Tech Campus

Operator not disclosed. Filed.

A proposed 633-acre data center campus next to several Lee Hill area neighborhoods is one of ten data center projects in Spotsylvania County's pipeline. It still needs a special-use permit before it can move forward.

Status
Filed
Operator
Not disclosed
Location
Lee Hill area, Spotsylvania Courthouse, Spotsylvania County, VA (approximate, city center)
Size
MW not reported, 633 acres
Cooling
Not reported
Utility
Dominion Energy
Last updated
August 1, 2026

Sources

What it would mean nearby

Deferred fuel cost recovery (docket PUR-2026-00078) is pending; Dominion Energy says it would add about $7 to $9 to a typical monthly bill. Data center cost allocation and transmission rider (docket PUR-2026-00056) adds about $0.94 a month to a typical bill, decided August 1, 2026. 2025 biennial review base rate increase (docket PUR-2025-00058) adds about $11.24 a month to a typical bill from January 2026.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

Dahlgren West Operator not disclosed
24 mi EApprovedKing George County, VA

Is it near you?