Hearing: December 4, 2026
Potomac Creek Campus
Joseph Metts. On hold
The Stafford Board of Supervisors voted 4-3 on July 7, 2026 to defer applicant Joseph Metts' three-building, 975,000 square foot data center and substation proposal on 99.3 acres off Eskimo Hill Road after a cemetery with Seddon family headstones and suspected graves of enslaved people was found on the property. On September 15, 2026 the Board voted 5-2 to extend the application review clock to December 4, 2026 to allow more time for the archaeological investigation to be reviewed by the Historical Commission, Planning Commission and Board of Supervisors. As of early November 2026 no new public hearing date has been announced and the project remains on hold pending that review.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Potomac Creek Campus changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- On hold
- Operator
- Not disclosed
- Applicant on record
- Joseph Metts
- Location
- south of the Stafford Technology Center, off Eskimo Hill Road, Stafford County, VA
- Size
- MW not reported, 99 acres, 975,000 sq ft
- Cooling
- Not reported
- Utility
- Dominion Energy
- Next hearing
- December 4, 2026, Stafford County Board of Supervisors
- Last updated
- November 9, 2026
What happens next
Paused by the developer, a regulator, or a court. It could resume, be withdrawn, or be replaced by a new filing on the same land.
Sources
- Historic Cemetery Prompts Deferral of Potomac Creek Campus Data Center Plans in Stafford, Potomac Local, 2026-07-09
- Stafford Historical Commission has 'major concerns' with Potomac Creek Campus data center project, Fredericksburg Free Press, 2026-07-17
- The New Battle for Potomac Creek, FXBG Advance
- Stafford splits 5-2 on Stafford One industrial site, extends Potomac Creek clock, Potomac Local, 2026-09-18
What it would mean nearby
Deferred fuel cost recovery (docket PUR-2026-00078) adds about $10.23 a month to a typical bill, decided September 29, 2026. Data center cost allocation and transmission rider (docket PUR-2026-00056) adds about $0.94 a month to a typical bill, decided August 1, 2026. 2025 biennial review base rate increase (docket PUR-2025-00058) adds about $11.24 a month to a typical bill from January 2026.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
History
Other tracked projects within 25 miles
Common questions
Where is the Potomac Creek Campus data center?
It is in Stafford, Stafford County, VA.
Has the Potomac Creek Campus data center been approved?
Not yet. It is on hold.
How big is the Potomac Creek Campus data center?
Reported size: 99 acres, 975,000 square feet.
When is the next public hearing?
December 4, 2026, Stafford County Board of Supervisors.
Corrections and tips: use the address in the footer. We link every claim to its source.