Hyperscale Data / Alliance Cloud Services Dowagiac Campus

Hyperscale Data (Alliance Cloud Services). Operating. 30 MW.

Hyperscale Data, through its subsidiary Alliance Cloud Services, operates a roughly 34 acre data center in the Dowagiac area of Cass County that the company says is already running about 30 megawatts of computing power. The company has announced plans to expand the site to 70 megawatts by 2027 and 340 megawatts by 2029, backed by agreements in principle with local utilities for more power. This is an existing, operating facility that is actively expanding rather than a new proposal.

Status
Operating
Operator
Hyperscale Data (Alliance Cloud Services)
Applicant on record
Hyperscale Data (Alliance Cloud Services)
Location
Dowagiac, Cass County, MI (approximate, city center)
Size
30 MW, 34 acres
Cooling
Not reported
Utility
Not reported
Last updated
August 29, 2026

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 30 MW facility would draw roughly 95,000 to 342,000 gallons of water a day, about what 1,100 households use.

For a noise estimate and the three distance rings, check your own address.

Follow this project

One email when Hyperscale Data / Alliance Cloud Services Dowagiac Campus changes status or a new filing lands within 25 miles of it.

Unsubscribe with one click. We do not sell the list.

Other tracked projects within 25 miles

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.