Is a Data Center Coming

Will County, IL

Joliet Technology Center

PowerHouse Data Centers (filed as Hillwood). Approved. 1800 MW.

Hillwood and PowerHouse Data Centers won an 8 to 1 Joliet City Council vote on March 20, 2026 to annex 795 acres near Rowell and Bernhard roads for a 20 billion dollar, four sub-campus data center park with up to 1.8 gigawatts of capacity. Construction is planned to begin in early 2027, and Joliet Residents For Responsible Growth filed a lawsuit in May 2026 challenging the rezoning as unconstitutional.

Status
Approved
Operator
PowerHouse Data Centers
Applicant on record
Hillwood
Location
Joliet, Will County, IL
Size
1800 MW, 795 acres, 6,900,000 sq ft
Cooling
Not reported
Utility
ComEd
Last updated
August 29, 2026

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 1800 MW facility would draw roughly 5.7 million to 20.5 million gallons of water a day, about what 65,600 households use.

This case does not change what a household pays today, but it is the main tool Illinois regulators are using to try to stop the cost of new grid equipment for data centers from landing on residential bills. ComEd annual reconciliation rate case (docket 25-0383) adds about $3.10 a month to a typical bill from January 2026. PJM capacity auction price spike hits ComEd supply charges adds about $10.50 a month to a typical bill from June 2025.

For a noise estimate and the three distance rings, check your own address.

Follow this project

One email when Joliet Technology Center changes status or a new filing lands within 25 miles of it.

Unsubscribe with one click. We do not sell the list.

Other tracked projects within 25 miles

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.