La Osa Project (Vermaland)
Vermaland LLC. Denied. 1000 MW.
Vermaland's La Osa project would have put a data center and power complex across 3,385 acres south of Eloy along the Greene Canal and Santa Cruz Wash. After sustained resident opposition, the developer cut the plan from 59 buildings and up to 3 gigawatts down to about 11 buildings capped at 1 gigawatt with water and cost concessions, but the Pinal County Board of Supervisors voted 4-1 on August 26, 2026 to deny the rezoning after nearly five hours of public comment, with 123 letters opposed versus 16 in support.
Follow this project
One free email when La Osa Project (Vermaland) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get an address report.
- Status
- Denied
- Operator
- Not disclosed
- Applicant on record
- Vermaland LLC
- Location
- South of Eloy along the Greene Canal and Santa Cruz Wash, near Red Rock, AZ, Pinal County, AZ (approximate, city center)
- Size
- 1000 MW, 3385 acres
- Cooling
- Not reported
- Utility
- Not reported
- Last updated
- September 2, 2026
What happens next
This proposal will not move forward as filed, but the land it was proposed on can be proposed again under a new project. See other stopped projects.
Sources
- 3,385-Acre La Osa Data Center and Power Complex Faces Rezoning Vote on April 16, Pinal Post, 2026-04-13
- Largest proposed data center in Arizona to be scaled back 80% after opposition, KJZZ Fronteras Desk, 2026-05-28
- Pinal County Advances Vermaland's La Osa Data Center Plan, Hoodline, 2026-04
- Pinal County rejects massive La Osa data center, residents want more rules for future projects, KJZZ, 2026-08-26
- La Osa Energy Center Denied by Pinal County Board of Supervisors, AZBEX, 2026-08-26
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 1000 MW facility would draw roughly 3.2 million to 11.4 million gallons of water a day, about what 36,500 households use.
For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.
Other tracked projects within 25 miles
Common questions
Where is the La Osa Project (Vermaland) data center?
It is in Eloy, Pinal County, AZ.
Has the La Osa Project (Vermaland) data center been approved?
No. A local government denied it.
How big is the La Osa Project (Vermaland) data center?
Reported size: 1000 MW, 3385 acres.
Is it near you?
Corrections and tips: use the address in the footer. We link every claim to its source.