Hearing: December 17, 2026
Prometheus
Meta. Under construction
Meta is building Prometheus, described as the world's first gigawatt capable data center, at 1500 Beech Road in New Albany; the campus is planned to include at least five data center buildings and Meta has said it is slated to come online in 2026. To help power Prometheus, developer Will-Power OH has applied to the Ohio Power Siting Board (case 26-0627-EL-BGN) for a 500 megawatt gas-fired power plant with 260 megawatts of battery storage in nearby Jersey Township, which drew a standing-room-only public hearing on October 6, 2026 where most speakers opposed the plant on environmental grounds. The evidentiary hearing on the power plant application was held as scheduled on October 21, 2026 before the Public Utilities Commission of Ohio in Columbus, with a board decision possible as early as the Ohio Power Siting Board's December 17, 2026 meeting.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Prometheus changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Under construction
- Operator
- Meta
- Location
- 1500 Beech Road, New Albany, OH, Licking County, OH
- Size
- MW not reported
- Cooling
- Not reported
- Utility
- Not reported
- Next hearing
- December 17, 2026, Ohio Power Siting Board
- Last updated
- October 26, 2026
What happens next
The site is under construction. The next step is opening.
Sources
- Meet Prometheus: World's highest capacity data center slated to open in Ohio in 2026, NBC4 WCMH-TV, 2026
- Public hearing draws some support and plenty of opposition to 500-megawatt power plant for data center, The Reporting Project (Licking County), 2026-10-08
- Hearing reveals deep divide over central Ohio data center power plants, Columbus Dispatch (via Yahoo News), 2026-10-15
- Case No. 26-627-EL-BGN Will-Power OH, LLC, Ohio Power Siting Board, 2026-10
History
Hearing: October 21, 2026
Other tracked projects within 25 miles
Common questions
Where is the Prometheus data center?
It is in New Albany, Licking County, OH.
Has the Prometheus data center been approved?
Yes, it was approved and is now under construction.
When is the next public hearing?
December 17, 2026, Ohio Power Siting Board.
Corrections and tips: use the address in the footer. We link every claim to its source.