Prime Data Centers. Under construction, 275 MW

Prime Data Centers is building a roughly 1 billion dollar, three building campus at 1600 East Higgins Road in Elk Grove Village, its first Illinois project, with up to 275 megawatts and more than 1 million square feet at full build-out. Elk Grove Village approved land sales and zoning changes for the project, which broke ground in November 2022 and has continued phased construction since.

How far is it from you?

Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.

Status
Under construction
Operator
Prime Data Centers
Applicant on record
Prime Data Centers
Location
1600 E Higgins Rd, Elk Grove Village, IL, Cook County, IL
Size
275 MW, 1,030,000 sq ft
Cooling
Not reported
Utility
ComEd
Last updated
August 29, 2026

What happens next

The site is under construction. The next step is opening.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 275 MW facility would draw roughly 872,000 to 3.1 million gallons of water a day, about what 10,000 households use.

This case does not change what a household pays today, but it is the main tool Illinois regulators are using to try to stop the cost of new grid equipment for data centers from landing on residential bills. ComEd annual reconciliation rate case (docket 25-0383) adds about $3.10 a month to a typical bill from January 2026. PJM capacity auction price spike hits ComEd supply charges adds about $10.50 a month to a typical bill from June 2025.

For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.

Other tracked projects within 25 miles

Common questions

Where is the Prime Data Centers Elk Grove Village Campus?

It is in Elk Grove Village, Cook County, IL.

Has the Prime Data Centers Elk Grove Village Campus been approved?

Yes, it was approved and is now under construction.

How big is the Prime Data Centers Elk Grove Village Campus?

Reported size: 275 MW, 1,030,000 square feet.

Corrections and tips: use the address in the footer. We link every claim to its source.