Project Open Sky (Cloverleaf Infrastructure)

Cloverleaf Infrastructure. Filed, 1500 MW

Cloverleaf Infrastructure's Project Open Sky is a planned 633.55 acre, six building data center campus of about 2.1 million square feet near Piedmont in Canadian County, part of a cluster of competing projects converging on the same OG&E transmission corridor west of Oklahoma City. The Piedmont City Council voted on October 22, 2026 to approve amended master design conditions, including a 75,000 gallon per day water use cap excluding fire suppression, a developer funded water study, about six miles of new sewer line, and a requirement that Frisco Road stay open. The council's final vote on rezoning and annexation for the project is now scheduled for November 12, 2026.

How far is it from you?

Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.

Status
Filed
Operator
Cloverleaf Infrastructure
Applicant on record
Cloverleaf Infrastructure
Location
Piedmont, Canadian County, OK (approximate, city center)
Size
1500 MW, 634 acres, 2,116,800 sq ft
Cooling
Closed loop (low water)
Utility
OG&E
Next hearing
November 12, 2026, Piedmont City Council (past)
First reported
2026-04
Last updated
November 2, 2026

What happens next

Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.

Sources

History

November 3, 2026

Hearing: November 12, 2026

October 12, 2026

Hearing: October 26, 2026

October 12, 2026

Size: 800 MW to 1500 MW

October 12, 2026

Status: rumored to filed

September 25, 2026

Added as rumored

Other tracked projects within 25 miles

Common questions

Where is the Project Open Sky (Cloverleaf Infrastructure) data center?

It is in Piedmont, Canadian County, OK.

Has the Project Open Sky (Cloverleaf Infrastructure) data center been approved?

Not yet. An application has been filed and has not been decided.

How big is the Project Open Sky (Cloverleaf Infrastructure) data center?

Reported size: 1500 MW, 634 acres, 2,116,800 square feet.

When is the next public hearing?

November 12, 2026, Piedmont City Council.

Corrections and tips: use the address in the footer. We link every claim to its source.