Project Spero
TigerDC. Withdrawn.
TigerDC announced a 3 billion dollar AI data center at the Tyger River Industrial Park in January 2026, then withdrew it a month later after heavy resident opposition and the county council moving to deny tax incentives.
- Status
- Withdrawn
- Operator
- TigerDC
- Applicant on record
- TigerDC
- Location
- Tyger River Industrial Park North, Spartanburg County, SC, Spartanburg County, SC
- Size
- MW not reported
- Cooling
- Closed loop (low water)
- Utility
- Lockhart Power
- First reported
- 2026-01-26
- Last updated
- February 27, 2026
Sources
- Company withdraws AI data center from Spartanburg County consideration, Fox Carolina, 2026-02-27