Is a Data Center Coming

Kendall County, IL

Project Steel Data Center Campus

Prologis L.P.. Approved

Prologis proposed an 18 building, 540 acre data center campus at the southeast corner of Galena Road and Eldamain Road in Yorkville, on unincorporated farmland. The Yorkville City Council approved Project Steel alongside the larger Project Cardinal on March 13, 2026 after a nearly six hour meeting, with the two projects together committing about 91 million dollars upfront, including 68.25 million dollars for the local school district.

How far is it from you?

Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.

Status
Approved
Operator
Not disclosed
Applicant on record
Prologis L.P.
Location
Yorkville, Kendall County, IL
Size
MW not reported, 540 acres, 9,000,000 sq ft
Cooling
Not reported
Utility
ComEd
Last updated
August 29, 2026

What happens next

Still to come: permits and construction. Builders do not always announce a construction start date in advance.

Sources

What it would mean nearby

This case does not change what a household pays today, but it is the main tool Illinois regulators are using to try to stop the cost of new grid equipment for data centers from landing on residential bills. ComEd annual reconciliation rate case (docket 25-0383) adds about $3.10 a month to a typical bill from January 2026. PJM capacity auction price spike hits ComEd supply charges adds about $10.50 a month to a typical bill from June 2025.

For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.

Other tracked projects within 25 miles

Common questions

Where is the Project Steel data center?

It is in Yorkville, Kendall County, IL.

Has the Project Steel data center been approved?

Yes, it has been approved.

How big is the Project Steel data center?

Reported size: 540 acres, 9,000,000 square feet.

Corrections and tips: use the address in the footer. We link every claim to its source.